IFS upgraded the building automation systems in multiple buildings for the Camdenton R-III School District in Camdenton, MO. Our scope of work for this project included equipment, labor, and materials to replace outdated building automation systems.
The customer’s existing building automation system (BAS) was outdated and not functioning properly. They were unable to receive adequate service and support for their existing systems, and contacted IFS for assistance.
Total Equipment Controlled
36 Rooftop Unit with new Reliable Controls
4 Rooftop Units with BACnet Integration
10 Air Handlers with Reliable Controls
2 Power Plants with Reliable Controls and BACnet Integration
Over 270 Reliable Zone Controllers
Additionally, during the Retro-Commissioning phase of the project, IFS discovered several energy saving opportunities including:
Variable Frequency Drives (VFDs) for Fans
Variable Frequency Drives (VFDs) for Pumps
Plant Optimization
At A Glance
CLIENT
Camdenton R-III School District
PROJECT
Automation Upgrade
LOCATION
Camdenton, MO
SERVICES PROVIDED
Building Automation System, Retro-Commissioning, Energy Upgrade